Overview
The Celtic Interconnector Project is a 700 MW, 500 km underwater cable being developed by the Celtic Interconnector Designated Activity Company. Once complete, the project will link Ireland and France via UK waters to progress the use of shared renewable energy between the two countries, potentially powering 450,000 homes.
Our work
RSK supported the design-and-build contractor with marine environmental, permitting, offshore fisheries and archaeological requirements by:
- creating commitment and permitting registers, marine construction environmental management plans and marine pollution prevention plans
- preparing and presenting environmental impact identification workshops
- providing inputs for permitting.
On-site work included an archaeology trial excavation at the landfall in Ireland and mobilisation of teams onto project vessels to achieve environmental and permitting compliance. A key challenge was to ensure that environmental and permit requirements for all countries were met, as the cable passes through French, UK and Irish waters; we provided expertise across all three countries. Support has also been provided for works taking place at the landfalls in Ireland and France, where overlap between onshore and offshore works was identified.
To date, we have enabled the client to fulfil the environmental and permit requirements across the three countries up to pre-lay and continue to provide this service as the project develops further.